Logicor Park Bolt 330 – Progress

With the existing building demolished, the skies are clear at Bolt 330, and work is progressing smoothly on the 330,000 sqft highly sustainable logistics unit for Logicor. The service yard is being laid, and the cut and fill operations have begun. The lift shaft has been installed and now stands ready to be surrounded by the upcoming steelwork.

Construction is advancing quickly, laying the groundwork for a state-of-the-art facility designed for efficiency and sustainability.

Project Sustainability Stats:

  • BREEAM – Outstanding
  • 94% of Materials Recycled
  • 57 Trees Planted
  • 8,000m³ of Earth Moved